From my experience the IPs can not be “in use” and should be “migrated off” any usage - prior to transfer.  Thank you all.


Philip A. Ward
917.886.2491
www.connexly.com/<https://www.connexly.com/>
www.linkedin.com/in/philward/<https://www.linkedin.com/in/philward/>

On Apr 25, 2019, at 11:36 PM, Philip Ward <philip at connexly.com<mailto:philip at connexly.com>> wrote:

Aside from ip justification from/with ARIN for the entity/isp receiving the space there should not be any issue on the transfer.  Happy to help and chat about process at anytime.

Thank you!


Philip A. Ward
917.886.2491
www.connexly.com/<https://www.connexly.com/>
www.linkedin.com/in/philward/<https://www.linkedin.com/in/philward/>

On Apr 25, 2019, at 11:31 PM, Owen DeLong <owen at delong.com<mailto:owen at delong.com>> wrote:



On Apr 25, 2019, at 20:44 , David Rodecker <dave at serverisp.com<mailto:dave at serverisp.com>> wrote:

Is there any requirement for an ISP to allow transferring IP's in use by a customer to another ISP?

Not only is there no such requirement, there’s actually pretty strong pressure not to allow it.

It causes fragmentation of the IP routing table which is considered problematic from a router memory perspective. Less so these days than in some years past, but still an issue.

In the telephone world, NANP requires local number portability such that a customer isn't beholden to a single carrier.

Changing phone number involves changing stationary, business cards, and all kinds of things that communicate with external parties and are hard to update.

Changing IP addresses is a pain, but if you’ve used DNS properly, it’s pretty easy to know where you need to update it and it’s not that problematic in most cases.

Case example: Long standing customer at a data center with a /24 IP block wants to move to another datacenter.

As a general rule, number portability isn’t going to be very useful here anyway.

Unless the customer wants prolonged down time, they’re going to want to move in stages and have some equipment at the new datacenter running in parallel. That means new numbers at the new datacenter anyway because the old numbers need to keep running and cutover is (usually) best accomplished after testing by DNS changes.

Owen

_______________________________________________
ARIN-Discuss
You are receiving this message because you are subscribed to
the ARIN Discussion Mailing List (ARIN-discuss at arin.net<mailto:ARIN-discuss at arin.net>).
Unsubscribe or manage your mailing list subscription at:
https://lists.arin.net/mailman/listinfo/arin-discuss
Please contact info at arin.net<mailto:info at arin.net> if you experience any issues.
_______________________________________________
ARIN-Discuss
You are receiving this message because you are subscribed to
the ARIN Discussion Mailing List (ARIN-discuss at arin.net<mailto:ARIN-discuss at arin.net>).
Unsubscribe or manage your mailing list subscription at:
https://lists.arin.net/mailman/listinfo/arin-discuss
Please contact info at arin.net<mailto:info at arin.net> if you experience any issues.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.arin.net/pipermail/arin-discuss/attachments/20190426/16411f1c/attachment.html>


More information about the ARIN-discuss mailing list